NYSDEC Oversight

The NYSDEC provides oversight of activities conducted by the major responsible parties at various Greenpoint petroleum remediation sites in Brooklyn, New York. NYSDEC’s subcontractor (Ecology and Environment Engineering and Geology P.C. [E&E]) conducts monthly field oversight of PRP activities to assist NYSDEC in developing a better understanding of the day to day investigation and remedial activities that occur in the Greenpoint area and report any pertinent issues to NYSDEC’s project manager.

The following sections summarize recent activities observed at the various Greenpoint remediation sites in Brooklyn, New York.

Date of Oversight Observation: November 11, 2026

 

Former ExxonMobil Terminal

Description of Activities

1.    E&E/WSP observed the ongoing site activities and observed conditions in Newtown Creek.

2.    Complete demolition of the on-site system is expected to begin once a fence is installed around the building.

3.    No sheens were observed in the creek adjacent to the Exxon bulkhead.

4.    Roux performs daily sheen checks along their bulkhead.

5.    The onsite treatment system is currently offline during the changeover to the new combined system.

 Planned Activities

1.    Onsite treatment system dismantlement.

 

ExxonMobil Off-Site Plume Area

Description of Activities

1.    CAC continued installation of the new treatment system building at 38 Varick Street with an approximately 25-person crew on site.

2.    The offsite treatment system is currently running with key onsite and offsite recover wells during the changeover to the new combined system.

Planned Activities

1.    Routine O&M activities.

2.    Installation of the new treatment system building to continue.

 

KM Terminal (Former BP Terminal)

Description of Activities

1.    Antea conducted a site walkthrough with E&E/WSP personnel.

2.    E&E/WSP did not observed any sheens located inside or outside of the bulkhead boom containment area.

3.    The containment boom was damaged at the treatment system effluent outfall at the northern end of the bulkhead. It appears to have torn in half and is no longer attached to the bulkhead.

4.    Carbon in stormwater unit A was replaced on 11/10/2026. A frac tank is on site to support backwashing units A and B.

 Planned Activities

1.    Routine O&M activities.

 

Former Paragon Oil Terminal/Apollo Street Creek Parcels

Description of Activities

1.    E&E/WSP inspected conditions along the upper, middle, and lower bulkheads, within the containment areas, and in adjacent Newtown Creek. Sheens were observed within the upper bulkhead containment areas. AECOM called subcontractor Mid-Atlantic to visit the site and deploy absorbent pads in this area.

2.    The groundwater treatment system is still offline.

 Planned Activities

AECOM informed E&E/WSP via email of the following:

1.    AECOM plans to replace faulty sensors in the clean backwash tank and the untreated water tank on 12/3 - 12/4.

2.    AECOM plans to install a vent in the oil-water separator room on 12/3 - 12/4.

3.    AECOM is working to schedule an electrician to update all equipment within the classified electrical areas of the remediation system to meet electrical code prior to startup.

4.    AECOM is planning to reattach the steel beam on the boom back to the bulkhead where the weld had broken off due to age. The section of the boom is temporarily tied to a post on the bulkhead as a preventive measure to keep this section of the boom above water. This repair is scheduled for 11/20.

5.    AECOM plans to submit a startup and sampling schedule to NYSDEC by 12/10.

 

Newtown Creek Observations

Meeker Avenue Bulkhead
E&E/WSP observed the conditions of Newtown Creek at the end of Meeker Avenue in the vicinity of the ExxonMobil Off-site outfall and adjacent storm outfalls. Storm outfall D was not discharging water. No sheens were observed in the vicinity, upstream and downstream of the outfalls. This observation took place approximately 3 hours before 10:20 AM 4.7’ AMSL high tide.

The NYSDEC provides oversight of activities conducted by the major responsible parties at various Greenpoint petroleum remediation sites in Brooklyn, New York. NYSDEC’s subcontractor (Ecology and Environment Engineering and Geology P.C. [E&E]) conducts monthly field oversight of PRP activities to assist NYSDEC in developing a better understanding of the day to day investigation and remedial activities that occur in the Greenpoint area and report any pertinent issues to NYSDEC’s project manager.

The following sections summarize recent activities observed at the various Greenpoint remediation sites in Brooklyn, New York.



Date of Oversight Observation: June 10, 2026

Former ExxonMobil Terminal

Description of Activities

1.    E&E/WSP observed the ongoing site activities and recorded current operating parameters of the on-site system from the control screen. 

2.    June’s discharge monitoring sampling to be completed on Thursday 6/11/26.

3.    E&E/WSP collected a sample of the on-site effluent for visual observation and compared it to a previously collected sample taken from the Newtown Creek in the vicinity of the outfall.

 Planned Activities

1.    Routine treatment system maintenance.

ExxonMobil Off-Site Plume Area

Description of Activities

1.    Access to the offsite treatment building property was restricted due to active crane operations for the construction of the new treatment building at 38 Varrick St. Foundation construction had been completed, and installation of the prefabricated building was observed to be in progress. Crane operations are expected to continue for approximately the next 6 weeks.

2.    June’s discharge monitoring sampling was completed on 6/09/26.

Planned Activities

1.    Routine treatment system maintenance.

2.    Installation of the prefabricated building to continue.

KM Terminal (Former BP Terminal)

Description of Activities

1.    Antea informed E&E/WSP that the groundwater treatment system and the product recovery pumps are running as designed.

2.    Groundwater Treatment System routine cleaning completed 6/8. OWS, EQ Tank, and DWSS (sump) all drained, cleaned, and refilled.

3.    Product/water was removed from Tank 35 via vac truck on 6/11. 2,850 gallons were removed and transported offsite for appropriate disposal.

 Planned Activities

1.    Routine treatment system and product recovery pump maintenance.

Former Paragon Oil Terminal/Apollo Street Creek Parcels

Description of Activities

1.    AECOM informed E&E/WSP via email that NYSDEC confirmed that the permit was under review with the Division of Water. NYSDEC confirmed on 6/2 that the permit application is still under review.

2.    The groundwater treatment system is still offline, and AECOM is waiting on the SPDES permit before testing the treatment system prior to start-up.

 Planned Activities

1.    AECOM informed E&E/WSP that they plan to conduct annual groundwater monitoring, semi-annual slab inspection, and free product recovery during the July 2026 shutdown of Empire Merchants.

Newtown Creek Observations

Former Paragon Terminal Bulkhead
E&E/WSP observed conditions along the upper, middle, and lower bulkheads, within the containment areas, and in Newtown Creek in the vicinity of the bulkhead. No sheens were observed in any of the containment areas or in Newtown Creek.

Meeker Avenue Bulkhead
E&E/WSP observed the conditions of Newtown Creek at the end of Meeker Avenue in the vicinity of the ExxonMobil Off-site outfall and adjacent storm outfalls. Storm outfall D was not discharging water. No sheens were observed in the vicinity, upstream and downstream of the outfalls (Photos 062026 - IMG_1869). This observation took place approximately 2 hours after 05:15 AM 3.9’ AMSL high tide.


This page was last updated on Tuesday, November 24, 2026.